Pipe Support Terminal External Corrosion

Pipe Support Terminal External Corrosion

West Africa

Pipe Details:

18” crude processing lines
20 bar operating pressure
Ambient temperature


Defect Details:

External corrosion due to both water entrapment and galvanic action at the support.


Repair Application:

Pipe could not be raised so blocks were inserted and the original pipe supports cut away and removed.  Pipe was then hand prepared using wire brushes and sandpaper.


Repair Time:

All three repairs were completed in 2 hours, new pipe supports were reinstated and the blocks removed.

18” pipe support repairs

3 repairs completed within 2 hours

HAVE A QUESTION OR NEED MORE INFORMATION? GET IN TOUCH.



Clock Spring has offices around the world with our global headquarters in Houston, TX, USA.

Have a question or need more information? Give us a call or fill in the form, and one of our representatives will reach out to you soon.

North America (USA)
621 Lockhaven Drive
Houston, TX 77073
P: +1-281-590-8491
F: +1-281-590-9528
England
4A The Causeway
Cambs, England
P: +44-1480-414-703
F: +44-1480-414-705
Scotland
54 Victoria Road
Aberdeen, Scotland
AB11 6FJ
P: +44 7985 396313
United Arab Emirates
P: +44-1480-414-703
F: +44-1480-414-705

Speak with an expert

Fields with * are required








Inquiry Reason:
Market Segment:
How Can We Help?*: